DETAILED ESTIMATE

METHOD OF TAKING OFF QUANTITIES:
 1. Long and short wall method
 2. Centre line method

Long and Short wall:
   The offsets are unsymmetrical and the building is more or less rectangular this method only is applicable.
The horizontal walls may be taken out-to-out and vertical walls in-to-in.

Centre line method:
   The total centre line length of walls in a buildings is calculated. By this method estimates may be prepared more 
quickly.



  DOOR - 1000*2100 
 CENTRE LINE
 Wall Thickness = 0.2m
Centre line length = 6 + 0.2/2 + 0.2/2
                                  = 4 + 0.2/2 + 0.2/2
 
Centre line Alround = 2(6.20+4.20)
                                      = 20.80

                  DETAILED ESTIMATE

SI

NO

DESCIPTION

N0

L

(m)

B

(m)

D

(m)

QTY

1.

Earth work Excavation

1

20.8

0.80

0.95

15.8 m3

 

 

 

 

 

 

 

2.

P.C.C 1:4:8

1

20.8

0.80

0.20

3.32m3

 

 

 

 

 

 

 

3.

R.R.masonry  C.M 1:6

 

 

 

 

 

 

Footing

1

20.8

0.60

0.75

9.36 m3

 

Basement

1

20.8

0.40

0.60

4.99 m3

 

 

 

 

 

 

14.35m3

 

 

 

 

 

 

 

4.

Earth Filling inside the Room

1

5.80

3.80

0.45

9.90 m3

 

 

 

 

 

 

 

5.

B.W  in C.M 1:4

 

 

 

 

 

 

Super Structure

1

20.8

0.20

3.00

12.4 m3

 

Parapet Wall

1

20.8

0.20

0.60

2.4 m3

 

Deduct

Door-1

 

1

 

1.00

 

0.20

 

2.10

 

-0.42 m3

 

 

 

 

 

 

14.5 m3

 

 

 

 

 

 

 

6.

R.C.C Roof slab 1:2:4

1

6.40

4.40

0.15

4.2 m3

 

 

 

 

 

 

 

7.

Plastering with C.M 1:3

 

 

 

 

 

 

Outside room

2(6.4 + 4.4)= 21.6

1

21.6

-

3.70

74.0 m3

 

Inside room

2(6 + 4)= 20

1

20.0

-

3.00

64.8 m3

 

Deduct

Door -1

 

1

 

1.00

-

 

2.10

 

-2.10 m3

 

 

 

 

 

 

136.7 m3

 

 

 

 

 

 

 

8.

Flooring

1

6.00

4.00

-

24.0 m2

 

 

 

 

 

 

 

9.

White Washing          Same quantity for         plastering.

 

 

 

 

 

136.7 m3